This study examined the assessment of inventory
management factors affecting construction project
delivery in Imo state, Nigeria. Adopting a descriptive
survey research design. The study population
comprised 800 construction professionals, including
architects, estate surveyors and valuers, site engineers,
materials purchasers, construction/project managers,
and contractors. Using the Taro Yamane formula, a
sample size of 267 respondents was determined through
judgmental sampling, while 243 valid questionnaires
representing a 91% response rate were retrieved and
analyzed. Data were collected through structured
questionnaires and analyzed using descriptive statistics
and multiple regression analysis with the aid of SPSS
version 23.
The findings revealed that theft and vandalization (β = -
0.177, p < 0.001), high carrying cost (β = -0.148, p =
0.020), insecurity (β = -0.169, p < 0.001), shortage of
materials (β = -0.137, p = 0.020), and inability to
determine the appropriate EOQ (β = -0.152, p = 0.002)
had significant negative effects on construction project
delivery. However, the use of traditional materials
management methods (β = -0.010, p = 0.876) was not
statistically significant. The regression model showed a
strong relationship between inventory management
factors and project delivery (R = 0.925), with the
identified variables explaining approximately 85% of
the variation in construction project delivery (R² =
0.850). The overall regression model was statistically
significant (F = 8.895, p = 0.002), confirming the
collective influence of inventory management practices
on project delivery.
The study concluded that effective inventory
management is critical to achieving successful
construction project delivery, with. Recommendation to
strengthen site security to minimize theft and
vandalization, adopting modern inventory management
systems and Materials Requirement Planning (MRP),
implementing Economic Order Quantity (EOQ)
techniques, engaging inventory management
professionals, and improving materials planning to
reduce carrying costs, prevent material shortages, and
enhance project performance.