# Cost-Benefit Analysis of a Proposed Small-Scale Waste-to-Energy Facility, Greater Accra.
## Overview
A cost–benefit analysis of a proposed 900 kW hybrid waste-to-energy facility at
Dodowa, Shai-Osudoku District, Greater Accra. The plant combines biogas digestion,
pyrolysis and solar PV to treat municipal solid waste and generate electricity.
The study is an ex-ante and comparative appraisal covering the institutional,
technical, commercial, financial and economic dimensions of the project.
## Method
Capital cost of GHS 29.6M was modelled against GHS 6.1M in annual revenue from
electricity sales, gate fees, compost and fertiliser over a ten-year horizon to
2035. Cash flows were inflation-adjusted using IMF International Financial
Statistics data and discounted at 10%.
## Results
| Metric | Value |
|---|---|
| Net present value | GHS 33.0M |
| Benefit–cost ratio | 1.53 |
| Discounted payback | 4.3 years |
| Avoided landfill and emissions benefits | ~GHS 3.6M per year |
## About
Final-year project work (ECON446), Department of Economics, University of Ghana,
September 2025. Graded A. Co-authored with Selina Egyinba Mensah and Richard
Asare, supervised by Dr. Owusu Adu Sarkodie.
The full report is in this repository.