Quantifying hazard resilience by modeling infrastructure recovery as a resource-constrained project scheduling problem

Domaine:

climate

Type de record:

paper
Créateur:
TayJorDiv
Éditeur:
Cop
Hôte:
Abstract. Reliance on infrastructure by individuals, businesses, and institutions creates additional vulnerabilities to the disruptions posed by natural hazards. In order to assess the impacts of natural hazards on the performance of infrastructure, a framework for quantifying resilience is presented. This framework expands upon prior work in the literature to improve the comparability of the resilience metric by proposing a standardized assessment period. With recovery being a central component of assessing resilience, especially in cases of extreme hazards, we develop a recovery model based upon an application of the resource-constrained project scheduling problem (RCPSP). This recovery model offers the opportunity to assess flood resilience across different events and also, theoretically, between different study areas. The resilience framework and recovery model have been applied in a case study to assess the resilience of building infrastructure to flooding hazards in Alajo, a neighborhood in Accra, Ghana. For the three flood events investigated (5-, 50-, and 500-year return periods) and the chosen standardized assessment period (300 d), the “300 d resilience” successfully shows a meaningful decreasing trend (0.94, 0.82, and 0.69) with increasing hazard magnitude. This information is most valuable for identifying the vulnerabilities of building infrastructure, assessing the impacts resulting in reduced performance, coordinating responses to flooding events, and preparing for the subsequent recovery. This framework expands upon prior work in the literature to improve the comparability of the resilience metric by proposing a standardized assessment period, the “n-time resilience”.

Visit

doi.org

Languages

Ga

Licenses

https://creativecommons.org/licenses/by/4.0/

Similaires

Strengthening Hazard Resilience: Building Capacity by Empowering Marginalized WomenProject Scheduling, Resource Allocation, and AI-Based Optimization as Drivers of Last-Mile Logistics Efficiency in NigeriaAn Improved African Vulture Optimization Algorithm for Dual-Resource Constrained Multi-Objective Flexible Job Shop Scheduling ProblemsSiliconHealth: A Complete Low-Cost Blockchain Healthcare Infrastructure for Resource-Constrained Regions Using Repurposed Bitcoin Mining ASICsSecure and Efficient Federated Learning for Predictive Modeling in Resource-Constrained Healthcare SystemsGenetic Algorithms with Simulation for a Job Shop Scheduling Problem with Crane Conveyance

Strengthening Hazard Resilience: Building Capacity by Empowering Marginalized Women

The empowerment of women to promote disaster risk reduction is a global concern. Poverty and gender

Project Scheduling, Resource Allocation, and AI-Based Optimization as Drivers of Last-Mile Logistics Efficiency in Nigeria

This study examines how resource allocation, project scheduling, and AI-based optimization interact

An Improved African Vulture Optimization Algorithm for Dual-Resource Constrained Multi-Objective Flexible Job Shop Scheduling Problems

According to the characteristics of flexible job shop scheduling problems, a dual-resource constrain

SiliconHealth: A Complete Low-Cost Blockchain Healthcare Infrastructure for Resource-Constrained Regions Using Repurposed Bitcoin Mining ASICs

This paper presents SiliconHealth, a comprehensive blockchain-based healthcare infrastructure design

Secure and Efficient Federated Learning for Predictive Modeling in Resource-Constrained Healthcare Systems

Background: Predictive modeling in healthcare holds promise for improving clinic

Genetic Algorithms with Simulation for a Job Shop Scheduling Problem with Crane Conveyance

Part 7: Operations Planning, Scheduling and Control International audience In this pa